Downtown Beautification Update 3/22

Post Date:03/22/2019 4:07 PM

Below is the Downtown Venice Beautification Update for Friday, March 22, 2019:

PHASE II - NOKOMIS AVENUE DRAINAGE PROJECT SCHEDULED TO BEGIN APRIL 1, 2019

On Monday, April 1, crews are scheduled to begin work on Nokomis Avenue between Tampa Avenue and W. Venice Avenue. Work in Phase II will include underground drainage installation, roadway reconstruction, utility work, and replacement of sidewalk and curb and gutter on Nokomis Avenue from Tampa Avenue to Pensacola Road. More details on the schedule of Phase II - Nokomis Avenue Drainage Project will be available next week.

DowntownWork1_3.22.19Current work

Crews continue landscaping, installation of sod, installation of lighted midblock crosswalks on W. Venice Avenue, and installation of ADA features at the crosswalks. The contractor is also completing punch list items throughout the project. Motorists should continue to expect single lane closures to allow crews to safely work.

Trash cans

The majority of the new trash cans have been installed throughout the project. As a reminder, these trash cans are for downtown visitors. Businesses are urged to use their dumpsters instead of the trash cans along the sidewalks. If you would like more information about dumpsters or trash pickup, please contact the City of Venice at 941-486-2422. 

DowntownWork3_3.22.19ALL DOWNTOWN ROADS ARE CURRENTLY OPEN!

For additional project information, please contact Jennifer Dorning, Project PIO, at 239-338-7723 or jennifer.dorning@atkinsglobal.com