Venice Road Bond Resurfacing Project UPDATE

Post Date:12/11/2017 8:52 AM
Concrete replacement and asphalt resurfacing is progressing well on the island of Venice for the Road Bond Resurfacing Project, Phase 1.
The contractor will be removing the old asphalt pavement and installing new asphalt pavement over the next two weeks on the following roadways:
• The Esplanade
• Barcelona Avenue
• Madrid Avenue
• Sarasota Street
• Nassau Street
• Tarpon Street
• St. Augustine Avenue
• Pensacola Road
• Milan Avenue
• Turin Street
• Verona Street
• Venezia Parkway
• Maggiore Road
• Armada Road South
• Sorrento Street
• Palermo Place
• The alley between Tampa Avenue and Nokomis Avenue
• The alley between Miami Avenue and American Legion Way
Please be aware that any private improvement such as landscaping or sprinkler heads directly against the roadway could be impacted during the pavement removal process. The contractor will be restoring the area after the paving process is complete, and your patience is greatly appreciated.
Please be prepared to move any parked vehicles from the roadway.